Production Progress Update 1115


#1

Nov 6/2018
Dear Community,

Sorry for the late report.

Our production capacity can already reach 60-70 units per day by October. However, the last batch of housing cannot meet our requirement. There are only 200 sets of qualified housing in the warehouse. We have to reduced the production temporarily to ensure the quality of the headsets.

We have 1000 sets of materials in factory. (except Housing). 3000 sets of materials to be delivered by November 15th.

Moreover, we have improved sourcing and testing of the housing.

We are now testing the new components from our supplier. New batch of housing will be available next week. By then, our capacity will reach 50 units per day. We plan to order more from the suppliers. With enough components, we can reach the full capacity and hire more production lines.

Increasing production capacity is our primary goal for now. The next goal is to reach 100 units per day / line by the end of November.

I will update you the production and delivery here 2-3 times a week.

You may find the production schedule as below picture and link.

https://drive.google.com/drive/folders/10DMw67FWU35Gla2fOt2t-3ShGnEg_2wl?usp=sharing

If you have any question about shipping/product, please submit your requests via Pimax service desk (Link: http://support.pimaxvr.com/) so the whole team can track the whole conversation of each request.

Many thanks for your support!

Yours sincerely,
Matthew | PimaxVR


Progress Update Discussion Nov 15/2018
Next batch details?
So much for the monday update...Pimax Missed the boat again
Progress Update Discussion Nov 15/2018
Progress Update Discussion Nov 15/2018
Progress Update Discussion Nov 15/2018
#2

#3

2 posts were merged into an existing topic: Progress Update Discussion Nov 6/2018


#5

#6

Closed Topic so it will only contain Production Progress updates. New Discussion Thread open.


#8

I’m sorry that some of production photos involve industry secrets. I will update them after our internal audit.


#9

Nov 7/2018
Dear Community,

Here are the production daily and production schedule for the last two days:

Production was suspended for 3 hours yesterday due to the production software breakdown, but it has been repaired. Please don’t worry.

Today’s production capacity has reached the schedule, and the headsets will enter warehouse tomorrow.

We will try to adjust production capacity this weekend to meet the production schedule this week.

https://drive.google.com/open?id=1CzSoT56g6Rb_NKJTO-3GxN-dJEEn7azW

Thank you

Yours sincerely,
Matthew | PimaxVR


Progress Update Discussion Nov 15/2018
#10

#11

Nov 12/2018

Dear Community,

Here are the production daily and production schedule for the past few days:

  1. The workers on the 7 day last week were working, producing 163 units in total. 43 units more than expected;

  2. Because the housing can arrive at the factory on Wednesday, so we focus on assembling modules today and tomorrow. When the housing arrived, we will arrange to assemble;

  3. Last Thursday, the factory sent 81 units to our logistics partners, who will arrange delivery in the next two days.

  4. On Sunday, the factory sent another batch and expected to arrive at the logistics partners on Wednesday. (specific quantities will be announced after arrival).

For details, please find the pictures and links below:

https://drive.google.com/file/d/1WI0_csby4ARUWE1jFfnT5CkG9bGkjUds/view?usp=sharing

Yours sincerely,
Matthew | PimaxVR


Progress Update Discussion Nov 15/2018
Progress Update Discussion Nov 15/2018
#12

Nov 13/2018

Dear Community,

Here are the production daily and production schedule for today:

  1. We have assembled 50 modules as pre-assembly today. Hosing will be in factory tomorrow, and it is expected to start assembling tomorrow afternoon.

  2. The headsets delivered last Sunday have arrived this afternoon. A total of 127 units will be sent to backers together. There are 55 units for 8K and 72 units for 5K+.

  3. The tracking number for this shipment will be received tomorrow by email.

For details, please find the pictures and links below:

https://drive.google.com/file/d/1-5HJxNWNh_AqIxPZi_MSwb9ZP-0dJK1D/view?usp=sharing

Thank you very much.

Yours sincerely,

Matthew | PimaxVR


Progress Update Discussion Nov 15/2018
Progress Update Discussion Nov 15/2018
#13

Nov 15/2018

Dear Community,

Here are the production daily report and production schedule for the last two days:

Nov 14:

  1. New housing arrived at the factory in the afternoon, so the production line only assembled 6 hours, a total of 26 units for 8K.

  2. Assemble 38 modules before new housing arrive.

Nov 15:

  1. Production capacity continues to climb, and it does not reach the expected 50 units, and a total of 31 units for 8K today.

  2. Assemble 25 modules.

  3. Tomorrow we will increase manpower to assemble the headsets.

For details, please find the pictures and links below:

Due to network problems, files can not be uploaded to Google drive. I will update it tomorrow.

Thank you very much.

Yours sincerely,

Matthew | PimaxVR


Progress Update Discussion Nov 15/2018